News

HS2 moves first huge Delta Junction viaduct section into place

84 metre steel viaduct section moving over the westbound link road

HS2 has moved the first huge viaduct section into place over the motorway network in North Warwickshire, marking a milestone for the project’s Delta Junction as HS2 reaches peak construction in the region.

Contractors working for HS2 have used a specialist push-pull technique to move the 84 metre, 300 tonne steel viaduct section into place over the westbound link road between the M6 and M42 near Coleshill.

This is the first of two moves to install the deck for HS2’s East Link Viaduct, which is part of the triangular Delta Junction. 

The second operation in April will create the full 158-metre-long composite deck over both westbound and eastbound motorway link roads. 

Further work, including in-situ concrete deck works and parapets installation will be undertaken to complete the structure.

It was delivered by specialist steelwork company Victor Buyck Steel Construction (VBSC), working on behalf of HS2’s main works contractor Balfour Beatty VINCI (BBV). 

Using a push-pull jacking system which gives greater flexibility during the launch operation, it was the first time VBSC have used their specially designed technique in the UK.

The team completed the move ahead of schedule in a total of 11.5 hours during a weekend closure of the motorway link roads. 

Working in close collaboration with National Highways, the roads were re-opened at 2.35am on Sunday.

Before the end of this year, a similar two-stage operation will move the identical West Link Viaduct which runs parallel to the East Link Viaduct.

This section of the triangular Delta Junction enables high speed trains to travel between London, Interchange Station in Solihull and Birmingham Curzon Street Station.

Stephen Powell, head of delivery - area north at HS2, said: “Building the East Link Viaduct in the Delta Junction is not only a key milestone for the HS2 project in the Midlands but is also critical to our earthworks mass haul strategy to keep construction traffic off the local roads.

“While we continue to construct HS2 in this area, it will provide a crossing route over the highway for construction vehicles to move excavated material from the Bromford Tunnel to other work sites in the Delta Junction, removing thousands of lorry movements from the local road network.”

The first launch takes the viaduct section to its halfway position over the westbound link road. 

Following completion of the first launch, three further steel girders will be welded to the back of the first structure, and 40 precast slabs will be installed on top of the girders. 

In April, this entire structure, weighing 1,100 tonnes will then be moved to its final position over both westbound and eastbound motorway link roads.

The Delta Junction is made up of embankments, cuttings and a total of 13 viaducts taking high speed tracks over motorways, local roads, existing rail lines, rivers and floodplains. 

 

If you would like to contact Karen McLauchlan about this, or any other story, please email kmclauchlan@infrastructure-intelligence.com.